Innovative Lifting Solutions for Challenging Canal Infrastructure Projects

GGR Group recently supported the Canal and River Trust in Reading by replacing four balance beams on the top and bottom lock gates. Drawing on extensive canal lifting experience, we developed a safe, tailored strategy, conducting a full site survey, risk assessment, and lift plan to address narrow pathways and limited working space along the canal edge.

Using the new Ganterud L5 Pro Levelling Yoke paired with the UNIC URW-706 Mini Spider Crane, the team lifted and installed beams up to 6.5 metres long with precision and efficiency. The L5 Pro’s automatic levelling system and radio remote control allowed safe tilting and positioning, reducing manual handling and enhancing safety. By combining innovative equipment with technical expertise, GGR delivered a smooth, reliable solution, supporting essential canal infrastructure work across the UK.